|
|
Reference |
Summary of main provisions |
|
Act |
Regu-
lation |
|
Existing dam |
Sec. 37 |
Sec. 4 |
- Dam completely constructed by the date of coming into force of the
Act;
- Dam under construction by the date of coming into force of the Act;
- Dam construction project for which the developer had, on the date of
coming into force of the Act, the required approval under the
Watercourses Act (R.S.Q., c. R-13).
|
|
Classification |
Sec. 14 |
Sec. 9 to 19 |
Every dam is classified on the basis of its vulnerability and the
consequences of its failure. There are five classes: A, B, C, D and E.
Class A dams are usually larger dams with higher failure consequences.
Only the dams in the Very Low Consequence category can be a Class E
dam.
A dam owner may request a review of the classification of the dam if a
report made under the responsibility of an engineer is submitted with the
request. |
|
Failure consequence category |
Sec. 14 |
Sec. 16 to 19 |
The dam failure consequence category must be determined, as the case
may be, by means of a dam failure analysis, rough mapping of the inundated
area or characterization of the area affected by the failure. There are
six consequence categories: Very Low, Low, Moderate, High, Very High and
Severe.
The consequence category shall be determined or reviewed prior to
authorization for construction, structural alteration, change in use or
stopping of the operation of a dam and following a dam safety review. |
|
Sec. 74 (2) |
On the date of coming into force of the Act, the Minister assigns a
consequence category to every dam. |
|
Minimum safety standards |
Sec. 15 |
Sec. 20 and 21 |
Floods: - the characteristics of a dam must
ensure resistance to no less than the safety check flood corresponding to
its failure consequence category:
- Very Low or Low Consequence Category: Ô
Safety check flood = 1 : 100 years;
- Moderate or High Consequence Category: Ô
Safety check flood = 1 : 1000 years;
- Very High Consequence Category: Ô
Safety check flood = 1 : 10 000 years or ½ PMF;
- Severe Consequence Category: Ô
Safety check flood = Probable maximum flood (PMF).
|
|
Sec. 22 |
- for a dam of which at least 50% of the inflow is controlled by
one or more upstream dams, the safety check flood shall take into
account the discharge capacity of the upstream dam;
|
|
Sec. 23 |
-
the safety check flood may be less for a given dam if an
analysis of the flows for lesser floods shows that a failure during
such floods would not cause incremental damages, that is when the
rise in the water level caused by the failure does not exceed 60
centimetres or when the incremental damages attributable to the dam
failure are not higher than those considered in the Low Consequence
Category;
|
|
Sec. 24 |
|
|
Sec. 25 |
-
the crest of an erodible dam, except for Severe Consequence
Category dams, must not be less than 1.0 metre above the safety
check flood level, unless the owner demonstrates that all hydrologic
and hydraulic uncertainties have been taken into account.
|
|
Sec. 28 and 29 |
Earthquakes: dams must be designed to remain stable during
the earthquake loading to which it may be subjected. A map of the
seismic zones is appended to the regulation. It includes the seismic
factors to be applied in the assessment of the dam stability in
earthquake conditions.
|
|
Sec. 75 |
Those safety standards (floods and earthquakes) must be applied to new
dams from the date of coming into force of the Act. For existing dams,
they must be applied following the dam safety review or when a structural
alteration requiring an authorization is performed if that alteration
occurs before the first safety review. |
|
Impounded water management plan |
Sec. 19 |
Sec. 30 to 34 |
An impounded water management plan must be drawn up by an engineer for
every dam except class E dams.
This plan shall describe all the procedures to be followed by the owner
for the safe management of the impounded water, in particular during
situations in which persons or property are at risk.
It must include, among other things, the full supply level, the level
of the safety check flood, the discharge curve, a description of the
measures that will be taken by the owner to manage the reservoir and,
where appropriate, a description of the communications strategy for
providing information on potential hazards to the people affected and to
the civil protection authorities.
This plan must be kept up to date and a summary forwarded to the local
municipality in which the dam is located. It must be drawn up before the
commissioning of a dam. |
|
Sec. 76 |
For an existing dam, the impounded water management plan must be drawn
up at the date the first dam safety review shall be conducted or prior to
authorization for structural alteration, change in use or stopping of the
operation of the dam. |
|
Emergency action plan |
Sec. 19 |
Sec. 35 to 40 |
An emergency action plan is required for every Moderate, High, Very
High and Severe Consequence Category dam.
This plan sets out the procedures to be followed for the protection of
persons and property upstream or downstream of the dam in the event of an
actual or imminent dam failure or to mitigate the effects of the disaster.
It must include, among other things, a list of the conditions that could
lead to a dam failure, a general description of the area that would be
inundated, the warning procedures and inundation maps.
This plan must be kept up to date and a summary forwarded to the local
municipality in which the dam is located. It must be drawn up before the
commissioning of a dam. |
|
Sec. 77 |
For an existing dam, a preliminary plan must be prepared within 1 year
of the coming into force of the Act and a final plan prepared at the date
the first dam safety review shall be conducted or prior to authorization
for structural alteration, change in use or stopping of the operation of
the dam. |
|
Monitoring |
Sec. 20 |
Sec. 41 to 45 |
Every dam must be monitored. Three types of monitoring activities are
fixed in the draft regulation:
- Site inspections (routine visual inspection to detect the more
apparent deficiencies): frequency varies from once a month for Class A
dams to once a year for Class E dams. Site inspections of Class A and
Class B dams shall be carried out under the supervision of a
civil-engineering technician or an engineer.
- Regular inspections (visual examinations of the dams and its
main components): frequency varies from 4 times a year for a Class A dam
to once a year for a Class D dam. No regular inspection is required for
Class E dams. Regular inspections of Class A and Class B dams shall be
carried out by a civil-engineering technician under the supervision of
an engineer. Regular inspections of Class C and Class D dams shall be
carried out by a civil-engineering technician or by a person familiar
with the dam under the supervision of a civil-engineering technician or
an engineer.
- Formal inspections (comprehensive visual examinations of each
component of the dam): frequency varies from once a year for Class A
dams to once every five years for Class D and Class E dams. This
inspection must be carried out by an engineer.
This provision applies to every dam from the date of the coming into
force of the Act. |
|
Dam logbook |
Sec. 21 |
Sec. 46 and 47 |
Every dam owner shall establish and maintain a logbook in which
activities (such as maintenance and inspections) and important events
relating to dam safety (such as floods and earthquakes) are recorded.
This provision applies to every dam from the date of the coming into
force of the Act. |
|
Dam safety review |
Sec. 16 and 17 |
Sec. 48 to 52 |
At regular intervals, every dam must undergo a safety review by an
engineer. The purpose of this review is to evaluate the safety, stability
and functionality of the dam, the conformity of its design and
construction with good practice and safety standards and to determine
appropriate remedial measures. The safety review must be conducted no
later than 10 years after the commissioning of the dam and updated at
least every 10 years. |
| |
Sec. 78 |
The first safety review for existing dams shall be conducted within the
time limit indicated below:
- 3 years after the coming into force of the Act for Very High and
Severe Consequence dams;
- 5 years after the coming into force of the Act for Moderate and High
Consequence dams;
- 7 years after the coming into force of the Act for Low Consequence
dams;
- 9 years after the coming into force of the Act for Very Low
Consequence dams.
If the condition of an existing dam is Good and the reliability of its
discharge facilities rated Acceptable, the owner may add 1 year to the
time limit indicated above. |
|
Safety program |
Sec. 23 to 27 |
Sec. 53 to 56
|
Dam owners who developed and implemented their own safety program may
submit that program to the Minister. If approved, it will replace some
safety standards.
Admissibility criteria:
- the owner owns at least 10 dams;
- the program has been in effect, under the responsibility of qualified
persons, for at least 5 years;
- the program covers all the dams belonging to the owner.
A program includes provisions relating to impounded water management,
emergency preparedness, monitoring, dam safety review, maintenance,
logbook and persons in charge of its implementation. |
|
Authorization |
Sec. 5 to 9
|
|
By the date of coming into force of the Act, the construction, the
structural alteration, a change in use likely to affect dam safety, the
removal and the permanent or temporary stopping of the operation of a dam
shall be authorized by the Minister. |
|
Sec. 10 |
Sec. 57 to 63 |
The plans and specifications for the project, prepared by an engineer,
must be submitted with the applications for authorization for the
construction and structural alteration of a dam. A certification, also
prepared by an engineer, that the work has been carried out in conformity
with the plans and specifications and any conditions of authorization
shall also be submitted to the Minister upon completion of the work.
Moreover, depending on the purpose of the authorization, hydrologic and
hydraulic studies and stability studies shall be submitted with
applications. |
|
Processing fees* |
Sec. 36 (4) |
Sec. 64 |
Authorization relating to the construction or structural alteration of
a dam: depending on the cost of the work requiring authorization (minimum
$1000) |
|
Sec. 65 |
Authorization for a change in use or a stopping of the operation of a
dam: $214 |
|
Sec. 66 |
Authorization for removal of a dam: Class A dams: $1068,
Class B dams: $534, Class C, D or E dams: $266 |
|
Sec. 67 |
Approval of remedial measures following a safety review: Class A dams:
$4269, Class B dams: $2669, Class C, D or E dams: $1068 |
|
Sec. 68 |
Approval of a safety program: $10,673 |
|
Annual fee* |
Sec. 36 (5) |
Sec. 69 |
Class A and B dams: $908
Class C and D dams: $187
Class E dams: $107 |